Now that this project has been approved by the Electricity Commission, Transpower has begun the process to identify a route for the new double-circuit transmission line.
The process by which a new line route is determined will include considerable consultation with potentially affected communities.
| Stage | Activity | When |
|---|---|---|
| Pre-work | Release of the Area Study report | Late July 2009 |
| Stage 1 | Release of the Route Options Report – setting out a number of different route options within the Area of Study for community feedback. |
18 September to 30 October 2009 |
| Stage 2 | Release of the Preferred Route Report – setting out a preferred route. | Late February 2010 |
| Stage 3 | Determine centre-line and envelope of transmission route within the preferred route. | Mid to late 2010 |