North Auckland and Northland Grid Upgrade Project (NAAN project)

Overview

What we're doing

Concrete truck and trench with workers laying cables. Sky tower in background.

Transpower is carrying out a project to reinforce its transmission network through Auckland and into North Auckland by installing the following cables and transformer.  Please click on link to be taken to the appropriate project:

The new cable link will provide an alternate electricity supply route to North Auckland and Northland, which presently relies on just one high capacity line between Otahuhu and Henderson for most of its power needs. The new transformer will reinforce Transpower's supply from Penrose.

Why we're doing it

This is a long term solution providing sufficient capacity for the foreseeable future.

Project Timeline

01.05.2009
Electricity Commission Approval
01.01.2010
Design Solution
22.03.2010
Cable Tender
25.11.2010
Award Cable Tenders
17.08.2011
Commence Installation
11.04.2013
Installation Complete
25.06.2013
Commissioning

Tendering

Tendering for this project (if any) will be made through either the GETS or Transpower website. Register at both these sites to be notified of any open tender release.

  • Project Reference:
    NAAN-TRAN-DEV-01
  • Region:
    Backbone
  • Status:
    Committed
  • Cost Bracket:
    G "$300 million plus"
  • Timing:
    2010 - 2014