Haywards substation is located on Haywards Hill in Lower Hutt, north of Wellington. It has two important functions: sending and receiving direct current (DC) electricity and sending alternating current (AC) for distribution to consumers.

The closest major electricity generation plants are in Taranaki and the central North Island, which predominantly supply the upper North Island. Haywards plays a very important role in ensuring electricity is distributed to where it is needed in the lower half of the North Island.

The construction of Pole 3 has special challenges as it will be undertaken in a live, operating substation.

REGIONAL MAP

Regional Map

LATEST NEWS

News image.

HVDC Pole 3 equipment in place

The major pieces of equipment for the HVDC Pole 3 project have now been installed.

News image.

Haywards Substation Community Newsletters

A regular newsletter designed to keep neighbours of Haywards Substation informed.

 

1 of 2

PROJECT TIMELINE

01.01.2010
Civil works starts
01.01.2011
Building construction starts
01.06.2011
Installation of primary plant begins
01.08.2012
Pole 1 decommissioning starts
05.12.2012
Site testing
16.02.2013
Pole 3 commissioned