TimingActivity
November 2009 - March 2011 Verify investigation assumptions with generators and lines companies.
June 2011 Release Request for Information Document for consultation.
29 July 2011 Submissions close on RFI document (timeline extended from 15 July)
End February/Early March 2012 Investment Test consultation.
April/May 2012 Submit Investment Proposal.