Lower South Island Grid Reliability Work

Monthly Snapshot

Ref: LWSI-TRAN-EHMT-01 
Investment Proposal to Electricity Commission May 2010
Electricity Commission Approval September 2010
Projected Commissioning Date 2011-2016
Monthly Update  
November 2011 Continuing work on preferred route and structure type.
October 2011 Continuing work on preferred route and structure type
September 2011 Continuing work on preferred route and structure type
August 2011 Working to have a preferred route and structure type by late September
July 2011 Project progressing according to schedule
June 2011 Continuing to discuss options with affected landowners.
May 2011 Released route and construction options for line from Gore to North Makarewa–Three Mile Hill line.
April 2011 Preparing for mailout to landowners and communities early May.
March 2011 None
February 2011 Working on information for route/construction consultation