| KMO-TRK-TRAN-EHMT-01 | |
|---|---|
| Investment Proposal to Electricity Commission | November 2009 |
| Electricity Commission Approval | 18 December 2009 |
| Projected Commissioning Date |
Summer 2011 - circuit |
| Monthly Update | |
| March 2012 | Project progressing according to programme. |
| February 2012 | Environmental applications lodged. Kaitimako transformer foundation pre-loading work completed. |
| December 2011/January 2012 | Construction contract awarded to Electrix. Contractor start up meeting held January 2012. |
| November 2011 | Installation tenders for main substation works received and are under evaluation. Lack of Transpower approved drawings for primary equipment at this stage may lead to later project delay. |
| October 2011 | Circuit commissioned late October. Installation tender specification for the main substation works has been completed and the tenders issued. |
| September 2011 | Preparing for final circuit commissioning in October |