Bunnythorpe-Haywards A and B Transmission Line Investigation

Consultation

Transpower is only at the initial stages of the investigation project and the timings below are indicative only:

DateActivity
August 2010 Draft needs report available.
Introduce project to landowners and stakeholders.
November 2010 Request for Information and Long List of Options Consultation Document
March - April 2011 Develop shortlist of options.
April 2011 Engagement with community and other stakeholders on short-listed options.
April - May 2011 Complete detailed cost analysis for each option and apply the Grid Investment Test.
September 2011 Select a preferred option.

October 2011


27 October 2011

Engage with community stakeholders and land owners on preferred option. Begin industry consultation on merits of investment.

Technical workshop

November 2011 Submissions on the merits of investment close, 8 November
December 2011 Seek Commerce Commission approval
2012-13 Project planning and environmental approvals.
2013 Project works commence.
2018 Project completed and lines commissioned.